Biscayne Point Neighborhood ROW Improvement - Miami Beach, FL




This Design-Build Neighborhood Improvement Project included the installation of over 24,000 LF of 8" to 16" DIP Water Main, and a Drainage System consisting of over 8,500 LF of drainage collection from 18" to 48" Diamater, 1 drainage pump station, over 1,000 LF of 24" PVC Drainage Force Main and 10 drainage wells. Limits of excavation for the pipe and stuctures varied in depth from 5ft to 13ft, and dewatering of the trenches via pumps was utilized as the water table began about 2-3 feet below ground surface. A&PCTE redesigned the stromwater system.

Owner or Agency:City of Miami Beach